- Assembly Demo: Demonstration of how the Interlock House is assembled.
- Feb 2nd-6th: Warmboard installation and roof framing.
- Feb 9th-13th: Roof module assembly.
- Feb 16th-20th: Roof assembly continues.
- Feb 23rd-27th: Completion of roof modules.
- March 2nd-6th: Moving roof modules from the warehouse, wall framing.
- March 9th-13th: Wall assemblies are put into place.
- March 23rd-27th: Moving lower modules from the warehouse.
- Module Lift: Lifting roof modules on top of the lower modules.
- Apr 27th-May 1st: Finals Week. Very little activity.
- May 18th-21st: Biobased Insulation and roof sheathing.
- Jun 29th-Jul 3rd: Roofing and interior work.