  • Assembly Demo: Demonstration of how the Interlock House is assembled.
  • Feb 2nd-6th: Warmboard installation and roof framing.
  • Feb 9th-13th: Roof module assembly.
  • Feb 16th-20th: Roof assembly continues.
  • Feb 23rd-27th: Completion of roof modules.
  • March 2nd-6th: Moving roof modules from the warehouse, wall framing.
  • March 9th-13th: Wall assemblies are put into place.
  • March 23rd-27th: Moving lower modules from the warehouse.
  • Module Lift: Lifting roof modules on top of the lower modules.
  • Apr 27th-May 1st: Finals Week. Very little activity.
  • May 18th-21st: Biobased Insulation and roof sheathing.
  • Jun 29th-Jul 3rd: Roofing and interior work.

This presentation contains no sound.

Get Connected:

Get connected Solar Decathlon on Facebook Interlock House on Twitter Interlock House RSS Feed
Major sponsors Iowa State University U.S. Department of Energy Solar Decathlon U.S. Department of Energy National Renewable Energy Laboratory